How to Price a Job Correctly: The Method That Actually Works

Underpricing is the leading cause of contractor business failure. Not slow markets, not bad clients, not competition — underpricing. You win the job, you do the work, you collect the money, and somehow you're still broke. The problem is almost always in the estimating. Here's the method that actually captures your true costs.

Start With Real Costs, Not Guesses

Get actual supplier quotes for materials — don't use last year's prices or rule-of-thumb numbers. Material costs have been volatile. A $50,000 job estimated with 18-month-old lumber prices can easily turn into a money-loser. Get quotes valid for the bid period. Add a materials contingency (5–10%) for price changes and waste.

Labor: Your Actual Loaded Cost

Calculate your true cost per hour for each employee. This is NOT their wage. It's wage plus: employer FICA (7.65%), workers' comp premium (varies by trade, can be 15–30% for framing), general liability insurance allocation, paid time off (if any), and any benefits. A carpenter at $28/hour may actually cost you $38–42/hour fully loaded. Use loaded rates in your estimates, not wages.

Subcontractor Markup

If you're coordinating and supervising subs, you're providing value beyond simply passing along their invoice. Standard markup on subcontractors is 10–20%. This covers your time coordinating their work, your risk (if they do bad work, you're on the hook with the client), and your overhead associated with managing their contract.

Build Your Own House? 42-page guide • 27 construction steps • 40+ years of field-tested knowledge
Get the Guide — $29

Overhead Allocation

Overhead is every cost of running your business that doesn't go into a specific job: truck payments, fuel, insurance, office expenses, software, phone, advertising, your own salary when not billing to jobs. Calculate your monthly overhead. Divide by the billable hours your crew works per month. That's your overhead rate per hour — add it to every job.

Profit Margin vs. Markup — The Terminology Trap

These are not the same. A 20% markup on $100,000 of costs = $20,000 added = $120,000 price. Your profit margin is $20,000/$120,000 = 16.7%, not 20%. If you want a 20% margin, you need a 25% markup. Many contractors "mark up 20%" thinking they're getting 20% margin and are actually getting 16.7%. At scale, this gap is significant.

Contingency

Every job has unknowns. A 5–10% contingency on the total estimate is reasonable for well-defined scopes. Complex renovations with unknown existing conditions warrant 10–15%. The contingency isn't padding — it's risk capital. If it's not needed, it becomes additional profit. If it is needed, it's the difference between breaking even and losing money.

The Bottom Line

Real materials + loaded labor + marked-up subs + overhead + profit + contingency = your price. Build a spreadsheet. Use it consistently. Raise your prices until you're winning 60% of bids — if you're winning 90%, you're too cheap.

Ready to Build Smarter?

Get the complete 42-page owner-builder guide — 27 construction steps from a builder with 40+ years experience and 1,000+ homes.

Get the Guide — $29
★★★★★
"I'm a retired teacher with zero construction background. Built a 1,800 sq ft house by myself using this guide and the consulting sessions."
— Patricia H., Asheville, NC

Free Building Tips — Straight to Your Inbox

Get practical construction advice from a builder with 40+ years and 1,000+ homes. No spam, ever.