Modern homes use more power than ever. Air conditioning, heat pumps, EV chargers, large kitchens with multiple circuits—it all adds up. Size panels correctly or you'll be upgrading in five years.
Understanding Amperage
Residential electrical service comes in standard sizes: 100A (old standard), 150A (still used), 200A (modern standard), 300A (luxury homes or future growth).
Each amp of service supports about 10 watts at 120V, or 24 watts at 240V. A 200A service supports roughly 48,000 watts total, though you don't use it all simultaneously.
Load Calculation
Start with fixed loads: water heater (4,500-5,500W), HVAC (3,000-5,000W), ranges/cooktops (5,000-10,000W), dryer (5,000-6,000W). Add laundry, circuit loads, and future needs.
Demand factor: You don't use all circuits simultaneously. Code allows you to de-rate combined loads. Typical demand is 80-100% of total connected load.
Modern Load Additions
Heat pump water heater: 240V, 4,500W. Higher demand than gas.
EV charger: 240V, 7,200-19,200W depending on speed. Increasingly standard.
Central AC and heat pump: 30-60A combined depending on capacity.
Induction cooktop: 240V, higher demand than traditional coil.
150A vs. 200A Services
150A: Adequate for basic homes without heat pumps or EV chargers. Fine for small to medium homes with electric heat.
200A: Standard for new homes. Supports modern equipment, allows future additions without upgrading.
When 200A Isn't Enough
Large homes (4,000+ sq ft) with multiple AC units, electric heat, and an EV charger might need 300A. Calculate first—don't guess.
Subpanels
If main panel space is tight or you have significant outbuildings, add a subpanel. Sized based on expected loads in that area. Properly sized feeder cable and breaker required.
Future-Proofing
Size panels for current needs plus 20% headroom. EV adoption will continue. Heat pumps are replacing furnaces. Panel upgrades are expensive ($2,000-5,000+). Get it right the first time.
Code and Standards
Current National Electrical Code (NEC) requires calculations based on connected load. Your electrician should provide a load calculation worksheet. Review it—it's the foundation of safe electrical design.
Meter and Service Entrance
The meter and service entrance must match panel size. If you upgrade from 100A to 200A, you might need to upgrade the meter, service entrance, and utility connection. Coordinate with your utility company early.
Cost Implications
Upgrading from 150A to 200A during construction adds roughly $500-1,000. Upgrading later costs $2,000-5,000 due to rework. Do it right from the start.
The Bottom Line
Panel sizing requires calculation, not guessing. Work with a licensed electrician who runs load calculations. Modern homes demand more power. Plan for it.