You open the excavation and the soil doesn't look like the geotech report said it would. Or the report told you what you had, and now you need to deal with it. Problem soils are a reality on many sites, and handling them wrong leads to foundation movement, drainage failures, and the most expensive type of construction callback there is.
Expansive Clays
Expansive clay is the most dangerous problem soil for foundations. It swells dramatically when wet and shrinks when dry — sometimes 5–10% volumetrically. This movement cracks slabs, pushes foundation walls, and destroys plumbing. Signs of expansive clay: plastic, slick-feeling soil that cracks when it dries, visible shrinkage cracks in existing grade, or a plasticity index (PI) above 20 in the geotech report.
Mitigation options: Remove and replace with non-expansive fill (most reliable). Deep foundation elements that bypass the active zone. Lime or cement soil treatment to reduce plasticity. Structural slabs designed to "float" over soil movement. For any significant expansive soil situation, engage a geotechnical engineer before designing the foundation.
Organic Soils and Fill
Topsoil, peat, decomposed vegetation, and construction debris are organic soils. They compress under load — sometimes years after construction — causing differential settlement. Never use organic material as structural fill. Never build on it without removal or mitigation. If the geotech log shows organic material (OL, OH, or PT classification) at footing depth, it must be removed and replaced with compacted engineered fill.
Existing fill is a related problem. Many sites have previous fill placed without engineering — construction debris, building demolition material, or simply soil pushed around during previous development. Old fill may have settlement potential that wasn't anticipated. If you encounter inconsistent material, stop and call the engineer.
Loose, Uncompacted Soil
Any soil that has been disturbed and not recompacted is a settlement risk. This includes trench backfill, retaining wall backfill, and soil disturbed during rough grading. Loose soil under footings or slabs will settle under load — sometimes dramatically. Specify and verify compaction at all structural fill locations. Get density tests (Proctor tests) to confirm you're hitting the required compaction percentage.
The Bottom Line
When the soil doesn't match the report, or when you expose something unexpected, the correct response is always the same: stop, document, call the engineer. The cost of a few hours of engineering consultation is trivial compared to the cost of a failed foundation.